All Collections
Tasks
FAQs
How do Task due dates work?
How do Task due dates work?

Because Tasks are part of a piece of work, there are 2 options to set the due date.

Erin Jamison avatar
Written by Erin Jamison
Updated over a week ago

Index

Due dates on an individual task

Each task in a work item can be given its own due date. This date can be selected from the calendar or by typing a date in the due date field.

If that work item is set up on a repeating schedule, all of the tasks will be given a due date that is the same number of days from the start date of the work item that the tasks from the original work item were in.

For example: If your original work item is due to start on January 1st and you have a task due January 8th, then that task in the future work item will be due 7 days after the start date of the future work item. 

Due dates in work templates

When you are setting due dates for tasks in templates, you can select a certain number of days before or after the work item start date. 

 
When you create a work item from that template, Karbon will update the Task due dates based on the new work start date.

Note: If your tasks are dependent on a previous section of completed tasks, consider using tasklist automators to trigger the appropriate due date based on the completed date of the previous set of tasks.

Did this answer your question?